Three hundred and eighty buildings

A few of them, by type. Every project page has the dates, the budget range and a client you can call.

One build

Twelve apartments in Zemun, week by week

  1. Foundations

    Weeks 1–6 · February

    Piling, because the river gravel is close. The only surprise of the project, and inside the contingency.

  2. Structure

    Weeks 7–22 · March to June

    Reinforced concrete frame, one floor every ten days, our own crew of fourteen.

  3. Roof and envelope

    Weeks 23–30 · July

    Dry by the end of July, which is what everything else depends on.

  4. Services and finishes

    Weeks 31–52 · August to January

    Plumbing, electrics, plaster, floors, kitchens. Twenty-two trades in sequence, on a board in the site office.

  5. Handover

    Week 58 · March

    Two weeks later than the plan — a lift delivery — and eleven days inside the contract date.

Renovation

A 1912 villa, back to brick and back again

BeforePhoto by Nolan Issac on Unsplash
Before After

Your project

A fixed price in two weeks

Send the drawings or describe the job. We visit, we quote, and the quote does not move.